APPLICATION OF CRITICAL PATH METHOD (CPM) TO OPTIMAL PROJECT SCHEDULING: A CASE OF MOSUL BUILDING COMPANY, YOLA NORTH LOCAL GOVERNMENT ADAMAWA STATE, NIGERIA

  • Usman Bitrus Danfulani
  • Mijinyawa Mohammed
  • B. Z. Reuben
  • Joshua Anche Yakubu
  • Shamsuddeen Iya Digil
Keywords: Critical Path Method (CPM), Project Management, Construction, Scheduling

Abstract

Project cannot be done without planning, scheduling and an estimation of its duration for completion. Every project that has to be undertaken must have a deadline for it completion but not every project goes as schedule. Hence, applications of scientific method such as CPM, PERT are often very useful in project management and scheduling. This study was on the application of CPM in scheduling a building construction taking a case study of Mosul Estate building construction. Analytical research design was adopted for the study as the design suit the study at hand. Secondary data of the activities, their descriptions and predecessor as while as their duration were obtained from the construction site. The network activities diagram, the forward and the backward pass obtained by the temporary ordered routing algorithm (TORA) were drawn and the critical path represented in bold arrow heads. The results show that if CPM is applied into the project, the project can be completed in 27 weeks compared to the initial duration of 32 proposed weeks by the company. This results if implemented by the management of the firm will save cost of labour and time. We recommend that CPM should be used in a building construction company before embarking on the building. The construction firm should devote more resources, labour and equipment to the critical path in order to avoid unnecessary delay and high cost of labour.

References

Andiyan. R. M., Glisima .D. R., and Hendy. T. (2020). Construction Project Evaluation Using CPM-Crashing, CPM- PERT and CCPM for Minimize Project Delays. Virtual Conference on Engineering, Science and Technology (ViCEST): Journal of Physics Conference Series: IOP Publishing DOI: https://doi.org/10.1088/1742-6596/1933/1/012096

Atin .S. and Lubis .R. (2019). Implementation of Critical Path Method in Project Planning and Scheduling.In IOP Conference Series Material Science Engineering: IOP Publishing 662 022031 DOI: https://doi.org/10.1088/1757-899X/662/2/022031

Bashuru M. and Douglas K. B (2022). Optimal Project Management Schedule for PhD Studies with Focus on Selected NorthernnSector Universities in Ghana Using CPM and PERT: American Journal of Operations Research: 12(1): 1-6

Burger M.( 2013). Project management in built Environment: The need for industry specific knowledge. Thesis, (PhD) university of the free state.

ChaoOu-Yang and Wang-LiChen, (2019).AHybridApproachforProject Crashing Optimization Strategy with Risk Consideration:ACaseStudyforanEPC Project:Mathematical Problems in Engineering,vol.2019,ArticleID 9649632,17pages, https://doi.org/10.1155/2019/9649632 DOI: https://doi.org/10.1155/2019/9649632

Chrzanowski, E. N. and Johnston, D. (1986). Application of Linear Scheduling and Engineering. Journal of Construction Engineering, 112(4), 476-491. DOI: https://doi.org/10.1061/(ASCE)0733-9364(1986)112:4(476)

Du Plessis, Y.(2014). Project construction management: A Behavioural perspective. Principle, practices and cases, Pearson Education south Africa.

Published
2023-07-09
How to Cite
Danfulani U. B., Mohammed M., Reuben B. Z., Yakubu J. A., & Digil S. I. (2023). APPLICATION OF CRITICAL PATH METHOD (CPM) TO OPTIMAL PROJECT SCHEDULING: A CASE OF MOSUL BUILDING COMPANY, YOLA NORTH LOCAL GOVERNMENT ADAMAWA STATE, NIGERIA. FUDMA JOURNAL OF SCIENCES, 7(3), 186 - 192. https://doi.org/10.33003/fjs-2023-0703-1860